Malaybalay City’s PHP20 Million IP Housing Project Nears Final Phase

Ang pabahay sa Malaybalay City para sa mga IP ay nasa huling yugto na, may mga susunod na plano na nakalatag.

Quezon City Urges Schools To Adopt Sustainable Practices Amid Climate Crisis

Tahasang hinikayat ng Quezon City ang mga paaralan na gawing bahagi ng kultura ng kanilang operasyon ang mga sustainable na praktis.

Negros Occidental Braces For Thousands At Holy Week Pilgrimage Sites

Naghihintay ang mga pilgrimage destinations sa Negros Occidental sa pagdating ng mga deboto para sa Mahal na Araw.

Sipalay Accommodations 90% Booked For Holy Week Break

Sipalay City, isang paboritong destinasyon, ay nag-uulat ng 90% na booking para sa Holy Week.

Suspension Lifted For P64-M Mati City Hall Project

By The Mindanao Life

Suspension Lifted For P64-M Mati City Hall Project

18
18

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The rehabilitated building of the Mati City Hall will finally be occupied within the month after Mayor Michelle Rabat lifted the suspension she earlier imposed on the project.

Rabat suspended all ongoing projects of the previous administration upon her assumption on June 30, 2019.

Rabat said she lifted the suspension on several of the projects that already undergone a forensic audit, including the PHP64.5 million City Hall building project.

The rehabilitation of the City Hall building was undertaken by Lotrim Construction, Inc. on Mar. 21, 2016 under the administration of then-Mayor Carlo Rabat.

Before the incumbent mayor’s assumption, the local government already paid the contractor PHP62.3 million.

In an Audit Observation Memorandum (AOM) released by the Commission on Audit on August 28, 2019, the agency noted that “bidding documents and all related documents forming part of the contract were not submitted to the COA Office contrary to the provisions of COA Circular No. 2009-001, particularly on the submission of contracts which must be within five working days from the execution.”

The COA recommended to the new mayor to “require the responsible officials/employees to immediately submit the bidding documents and the supporting documents for the payments to Lotrim Construction”.

Rabat said the contractor already met with local officials to complete the project.

Rabat also recently ordered the termination of the PHP25-million contract for the improvement of the FGR Park and Baywalk that was entered into by the previous administration for failure to utilize the amount within the prescribed period. (PNA)