BARMM Turns Over PHP25 Million Public Market To Maguindanao Del Norte Town

Malugod na tinanggap ng Upi ang PHP25 milyon na proyekto mula sa BARMM, nagbigay ng oportunidad para sa mas magandang kabuhayan.

DOH Deploys New ‘Barrio’ Doctors To Lanao Del Norte

Ipinadala ng DOH ang bagong batch ng mga doktor sa Lanao del Norte upang matugunan ang mga pangangailangan sa kalusugan ng komunidad.

CCC Urges LGUs To Fully Utilize NAP, PSF To Boost Climate Resilience

Hinimok ng Climate Change Commission ang mga LGUs na isama ang NAP at PSF sa kanilang mga estratehiya para sa katatagan sa klima.

The Power Of Potatoes: A Nutrient-Rich Staple In Filipino Cuisine

Ang patatas ay hindi lamang isang side dish kundi kasama sa ating kalusugan at enerhiya.

Suspension Lifted For P64-M Mati City Hall Project

By The Mindanao Life

Suspension Lifted For P64-M Mati City Hall Project

12
12

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The rehabilitated building of the Mati City Hall will finally be occupied within the month after Mayor Michelle Rabat lifted the suspension she earlier imposed on the project.

Rabat suspended all ongoing projects of the previous administration upon her assumption on June 30, 2019.

Rabat said she lifted the suspension on several of the projects that already undergone a forensic audit, including the PHP64.5 million City Hall building project.

The rehabilitation of the City Hall building was undertaken by Lotrim Construction, Inc. on Mar. 21, 2016 under the administration of then-Mayor Carlo Rabat.

Before the incumbent mayor’s assumption, the local government already paid the contractor PHP62.3 million.

In an Audit Observation Memorandum (AOM) released by the Commission on Audit on August 28, 2019, the agency noted that “bidding documents and all related documents forming part of the contract were not submitted to the COA Office contrary to the provisions of COA Circular No. 2009-001, particularly on the submission of contracts which must be within five working days from the execution.”

The COA recommended to the new mayor to “require the responsible officials/employees to immediately submit the bidding documents and the supporting documents for the payments to Lotrim Construction”.

Rabat said the contractor already met with local officials to complete the project.

Rabat also recently ordered the termination of the PHP25-million contract for the improvement of the FGR Park and Baywalk that was entered into by the previous administration for failure to utilize the amount within the prescribed period. (PNA)