Sama-Badjao Community In Surigao Get Houses

Sa tulong ng DHSUD, nakatanggap ng mga tahanan ang 20 pamilyang Sama-Badjao sa Surigao. Isang tala ng pag-asa sa buhay.

“Incognito” Tops Netflix PH; Debuts Strongly On Free TV

The newest series "Incognito" has sparked excitement with action sequences that leave viewers on the edge of their seats.

Knowledge Channel Drops New Episodes of Robi Domingo’s Math Show “MathDali”

Knowledge Channel Foundation is proud to introduce the latest episodes of "MathDali," making math accessible and fun for students everywhere.

Surigao City Collects PHP109.8 Million Taxes, Fees Under BOSS Program

PHP109.8 milyon ang nalikom ng Surigao City sa BOSS program. Tagumpay ng lokal na ekonomiya.

DOE Exec Sees Normalization Of Luzon Power Supply

By The Mindanao Life

DOE Exec Sees Normalization Of Luzon Power Supply

6
6

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

Energy Undersecretary, Felix William Fuentebella has discounted another yellow alert status for the Luzon grid on Wednesday, as maintenance works on the Malampaya gas field in offshore Palawan is expected to end Tuesday.

“We don’t see any yellow alert status for tomorrow because of the additional 1,620 MW (megawatts) from the natural gas plants,” he told journalists in a Viber message Tuesday.

“We expect the completion of Malampaya maintenance today, 15 October 2019. Once gas supply is available, Ilijan Blocks A and B (2 x 600MW) and San Gabriel (420 MW) will be operation starting tomorrow,” he added.

The Malampaya gas field was on maintenance shutdown since October 12, 2019.

Yellow alert was again raised in the Luzon grid on Monday due to large power supply deficiency partly due to the Malampaya maintenance shutdown.

Forced outage for the day affected capacity reaching 1,163 megawatts (MW) based on the total installed capacity of five power plants that include the Sual coal-fired power plant.

Team Energy Corporation’s (TEC) 647 MWs have been on forced outage due to condenser tube leak since last October 11.

Fuentebella said “Sual Unit 1, as per their report yesterday, (said) they are targeting to complete the repair and ‘washing’ of turbine by 21 or 22 October 2019.”

“PMS (preventive maintenance schedule) of Sual Unit 2, which is scheduled to start on 19 October 2019 and end on 17 November 2019, will be moved until Unit 1 is available and stable,” he added. (PNA)